Defects Liability Period (DLP) reminder. All new HDB BTO flats are
covered by a 12-month DLP from key collection. New condo units carry a developer-defined
DLP, usually also 12 months. Submit defects within 30 days of key collection
via the Mobile@HDB app, your nearest Building Service Centre (BSC), or by scanning the
QR code in your Welcome Kit. Do not start renovation until defects are closed
— once renovation begins, HDB may attribute new defects to your contractor, not the original
builder.
🚪 Doors & Windows
All properties
Main door opens outward (HDB regulation), closes smoothly without rubbing
Main door peephole and door viewer functional
All internal doors close smoothly, hinges aligned, no warping
Door locks engage cleanly, keys turn easily
Bomb shelter (household shelter) door rubber seal intact, no gaps
Bomb shelter ventilation openings clear of obstruction
Window panes free of cracks, scratches or chips
Window frames and seals watertight (test with water spray)
Window restrictors and safety stoppers working (kitchen / service yard)
Window grilles (if installed) firmly secured
🧱 Walls, Ceiling & Flooring
All properties
Walls free of cracks, dents, scratches, or peeling paint
No water stains on walls or ceilings (especially under bathrooms above)
Ceiling free of hairline cracks, sagging, or visible joints
False ceiling (if any) firmly anchored, no movement when pressed
Floor tiles aligned, no hollow sound when tapped (tap every tile)
Tile colour consistent, no obvious shade variation
Grout lines clean, evenly applied, no cracks or gaps
Skirting tightly fitted to walls and floor, no visible gaps
Floor level even (roll a marble — should not roll consistently in one direction)
Vinyl flooring (if OCS opted): no lifting edges, scratches, or seams
🚿 Bathrooms & Wet Areas
All properties
Floor traps drain water within 30 seconds (flood the bathroom and check)
Bathroom floor slopes correctly toward floor trap
Shower mixer hot and cold functions both working correctly
Shower head pressure adequate
Toilet flush fills tank in 3–5 minutes, no leaks at base
No water seepage around toilet base or pipe connections
Basin pipes free of leaks (run water for 2 minutes, check under sink)
Wall tiles bonded firmly (tap every tile — hollow = potential failure)
Waterproofing intact at floor-wall joints
Mirror, vanity and accessories firmly mounted
Toilet bi-fold door (HDB) opens fully, recessed handles functional
Ventilation fan working (if installed)
🔌 Electrical & Lighting
All properties
Every power socket tested with phone charger or appliance
All light fittings functional, no flickering or buzzing
Light switches feel firm, not loose
Doorbell rings clearly inside the flat
Distribution board (DB) labels match the circuits they control
Residual Current Device (RCD) trips when test button pressed
No exposed wiring or unsealed conduit ends
Home Fire Alarm Device (HFAD) on ceiling tested — light blinks, alarm sounds
Aircon points pre-installed (if applicable) — capped and labelled
TV and data points functional
🍳 Kitchen & Utility
All properties
Kitchen sink drains fast, no slow drainage or gurgling
Sink pipes free of leaks under cabinet
Gas point in working order (turn on briefly, smell-check)
Service yard floor slopes correctly toward drain
Refuse chute opens and closes smoothly (HDB only)
Wall tiles aligned, no chipped corners or uneven grout
Aircon ledge slopes outward, no signs of water seepage
Built-in kitchen cabinets (if OCS opted): laminates free of peeling, doors aligned
Cabinet hinges, drawers and handles function smoothly
🏢 Condo-Specific
Condo only
MCST joint handover inspection scheduled with managing agent
Balcony drainage clears within 60 seconds when flooded
Balcony floor slopes toward drain (not toward unit)
Glass balustrade panels secure, no chips or cracks
Pre-installed air-con system tested — cooling and condensate drainage
Air-con remote and thermostat functional
Intercom / video phone to lobby and guard house working
Smart home features tested (digital lock, smart switches, if applicable)
Built-in wardrobes, kitchen cabinets, vanity carpentry — drawers, hinges, alignment
Defect report submitted to developer's DLP team within stated window
📝 Documentation & Reporting
All properties
Mark every defect on-site with painter's tape labelled with marker
Photograph every defect — close-up + wide shot — with timestamp
Compile defects into the HDB Defects Feedback Form or Mobile@HDB app
Submit within 30 days of key collection (HDB strongly recommends ASAP)
BSC will arrange a joint verification inspection
After rectification, attend closing inspection — verify all defects fixed
Do not hand over flat keys to contractors; bring a padlock for security
Do NOT begin renovation until defects rectification is closed
How to report your defects to HDB
1
Mobile@HDB app: Download the official HDB app and submit your defects digitally with photos attached. Fastest option for most homeowners.
2
Scan QR code in Welcome Kit: HDB provides a QR code in your Welcome Kit or on a notice in your kitchen — scan to access the online rectification form directly.
3
Visit your Building Service Centre (BSC): Walk-in submission at the BSC located within your BTO project. Bring your defect list with photos.
4
Joint inspection: BSC will arrange a joint inspection with you and the contractor to verify reported items, typically within 2 weeks.
5
Rectification: HDB contractor carries out repairs at no cost to you. Most rectifications complete within 2 weeks of joint inspection.
6
Closing inspection: Verify every defect is fixed properly. Sign off only when satisfied. Re-report anything unsatisfactory.
Official references & resources